BY DEBORAH LAVERTY
dlaverty@nwitimes.com
219.762.1397, ext. 2223 | Wednesday, April 23, 2008 | (3 comment(s))
HOBART | The start of the workweek Monday also will be the official start of the 61st Avenue road construction project, city officials said.
Once started, the entire project is expected to take 18 months translating to road closures and detours for at least five months of that period, Assistant Fire Chief Steve Mast said.
"The contractors will be working on the bridge and widening the road all at the same time. There will be a flurry of activity," Mast said Tuesday.
The $6.9 million project calls for widening and improvements to 61st Avenue starting at Marcella Boulevard on the west and ending just east of Colorado Street, City Engineer Steve Truchan said.
Work at the 61st Avenue/Colorado Street intersection, starting east of Liverpool Road, will entail building a 16-foot wide, 8-foot tall concrete culvert-style bridge over a dipped portion of the roadway, Truchan said.
The 61st Avenue bridge construction site will begin roughly at the Elks Club and continue east past the Colorado Street intersection, he said.
That portion of the construction site will be closed to all traffic for about five months.
Other improvements to 61st Avenue will include adding new storm sewers, streetlights and curbs, he said.
City officials have made provisions for emergency crews who need to get to St. Mary Medical Center east of the project on 61st Avenue and Ind. 51, Mast said.
Emergency crews will be allowed to go around the closure by entering the western side of Amber Creek subdivision, which is north of the Colorado Street/61st Avenue intersection, he said.
The crews will then re-enter farther east on 61st Avenue at a street that would take them beyond the construction area, he said.
In addition, St. Mary Medical physicians also will be given a placard which will allow them passage around the closure provided it is for an emergency, police Lt. Steve Houck said.
"If a doctor is on an emergency run he or she can get through also. ... If others try and get through they'll be ticketed," Houck said.
The bulk of the 18-month project will be completed this year with some of the work, such as the striping, finished in 2009, HNTB Corp. project engineer Ted Behrens said.
Behrens and Truchan said the decision to close the intersection for several months while work is going on was made several years ago to decrease the cost of the project.
Back to story 3 comment(s)
- It wasn't clear, concise or focused on the topic in the story.
- It was a personal attack, vulgar, explicit or degrading, used actual or implied profanity or contained potentially libelous statements.
- It accused someone of being guilty of a crime.
- It promoted violence or illegal acts.
- It contained telephone numbers or street addresses, or e-mail addresses and links to Web sites other than nwi.com or government agencies.
In no way do these comments represent the views of The Times or Lee Enterprises.
Passionate views, pointed criticism and critical thinking are welcome. Name-calling, crude and profane language and personal abuse are not welcome.
Reader comments will not be edited - they will be approved or declined. They may be used in the print edition of the newspaper.
If you feel a posted comment has violated these guidelines, please email our New Media team the commenter's name, the comment and a link to the article.
For more information please read our Terms of Service.



The village... wrote on Apr 23, 2008 9:17 PM:
I really wish ALL construction could be done in sequences, with minimal disruption.
The 73 rd street incident there WAS no notice. I take that street twice a day. I go by in the morning, nothing, I come home and it's a TRAIN wreck!
Please try and be considerate to the taxpayers, that's OUR money and yours that you're spending.
GIVE SOME NOTICE!
"
what about rd wrote on Apr 23, 2008 9:15 AM:
nd Place Resident wrote on Apr 23, 2008 7:43 AM:
"